Planning

SCHEDULE 
  • Started end June 2015
  • Will end in June 2020
  • Float purchase call for tender issued end of July 2015
  • NKE won the tender.

MOCCA Gantt Chart

Milestone 

Number

  Milestone

  Name

Workpackage(s)

involved

Expected

Date

Means of

Verification

Status

M 2.1

Float Procurement Tender on JOUE

WP2

Mo 01

Text of the Call D 2.1

Done

M 2.2

Selection of Float Manufacturer and Order

WP2

Mo 03

Selection Report D 2.2

Done

M 2.3

Reception of Lot 1 (50 floats)

WP3

Mo 08

See D 2.3

Done

M 2.4

Reception of Lot 2 (100 floats)

WP3

Mo 14

See D 2.4

Done

M 2.5

Start of Float Deployment

WP3

Mo 12

See Deployment Plans D 3.2.1

Done

M 4.1

Start of Float Processing in RT

WP4

Mo 12

First Data delivered to Argo

Done

M 4.2

Start of Float Processing in DM

WP4

Mo 24

First Delayed-Mode Data Delivered to Argo

To be done